HAUSE SEWER NETWORKsewers@hause.ca403-679-3100
TrenchlessSewer.ca
New-path methods

Auger boring and pipe ramming: driving a casing under the road

How auger boring and pipe ramming install steel casings under roads and rail: bore pits, sizes, lengths, accuracy, ground limits and carrier pipes.

Short answer

Auger boring jacks a steel casing through the ground from a bore pit while auger flights inside it carry the spoil back; pipe ramming hammers an open-ended steel casing in with a pneumatic tool and cleans the soil core out afterwards. Both install casings between two pits, mostly under roads, railways and embankments, and a carrier pipe is then set to grade inside the casing.

Key takeaways
  • Auger boring is the most common way to cross roadways with storm, sanitary and water pipes, according to the Iowa SUDAS manual.
  • Common auger-bore sizes are 8 to 36 inches with typical bores of 175 to 225 feet; ramming handles 2 to 55 inches, usually under 150 feet.
  • Both hold about ±1% of bore length; steered auger equipment improves to about ±0.1% vertically.
  • Ramming copes with cobbles better than augering; neither suits solid rock.
  • For gravity sewers, the carrier pipe is set to grade on chocks inside the casing, often an oversized one.
Auger boring and pipe ramming comparedLeft: auger boring. A long bore pit holds a track-mounted boring machine braced against a backstop. It jacks a steel casing forward while auger flights turning inside the casing carry the spoil back to the pit. Right: pipe ramming. A pneumatic hammer on guide rails strikes the back of an open-ended steel casing, driving it through the ground; the core of soil inside the casing is cleaned out afterwards. Below, a carrier pipe sits on chocks inside the casing so it can be set to the required grade. AUGER BORINGcasing jacked · spoil augered back PIPE RAMMINGcasing hammered · soil core cleaned out MACHINE ON TRACK SPOIL CARRIED BACK ±1% OF LENGTH · STEERED ±0.1% VERT. HAMMER ON RAILS SOIL CORE NON-STEERABLE · ±1% OF LENGTH CARRIER PIPE ON CASING CHOCKSset to grade inside the casing, then theannulus is filled if the design calls for it SECTIONS NOT TO SCALE · TOLERANCES: IOWA SUDAS DESIGN MANUAL CH. 14
Fig. 1Auger boring and pipe ramming both drive a steel casing between two pits; the carrier pipe is then set to grade inside the casing on chocks.

01 /Why install a casing at all?

A casing is a sleeve, usually steel, that carries the pipe that actually does the work, called the carrier. Road and rail authorities often require casings at crossings so the carrier can be replaced later without disturbing the road, so a leak runs out the ends rather than washing out the embankment, and so the carrier is protected from loads. Auger boring and pipe ramming are the workhorse methods for putting that casing in.

Auger boring and pipe ramming comparedLeft: auger boring. A long bore pit holds a track-mounted boring machine braced against a backstop. It jacks a steel casing forward while auger flights turning inside the casing carry the spoil back to the pit. Right: pipe ramming. A pneumatic hammer on guide rails strikes the back of an open-ended steel casing, driving it through the ground; the core of soil inside the casing is cleaned out afterwards. Below, a carrier pipe sits on chocks inside the casing so it can be set to the required grade. AUGER BORINGcasing jacked · spoil augered back PIPE RAMMINGcasing hammered · soil core cleaned out MACHINE ON TRACK SPOIL CARRIED BACK ±1% OF LENGTH · STEERED ±0.1% VERT. HAMMER ON RAILS SOIL CORE NON-STEERABLE · ±1% OF LENGTH CARRIER PIPE ON CASING CHOCKSset to grade inside the casing, then theannulus is filled if the design calls for it SECTIONS NOT TO SCALE · TOLERANCES: IOWA SUDAS DESIGN MANUAL CH. 14
Fig. 2Auger boring (left) removes spoil through the casing as it is jacked forward; pipe ramming (right) hammers the casing in and removes the soil core afterwards. Below, the carrier pipe on casing chocks.

Once the casing is in, the carrier pipe is fitted with casing chocks, spacers that centre it and hold it off the casing wall, and pushed or winched through. The Iowa SUDAS manual notes that the chocks let a contractor correct the carrier's grade inside a casing that is slightly off, and that an oversized casing gives more room to do so where accuracy matters.

02 /How does auger boring work?

  1. Dig the bore pit and receiving pit

    SUDAS gives typical bore-pit sizes of 26 to 40 feet long and 8 to 12 feet wide, about 8 to 12 m by 2.5 to 3.5 m, with a crushed-stone base to support the machine.

  2. Set the track to line and grade

    The boring machine slides on a master track set to the exact line and grade. This is the critical step, because there is little ability to correct once the bore starts.

  3. Brace against a backstop

    Hydraulic rams thrust against a backing plate of steel piling, steel plate or timbers; long or large bores may add a concrete backstop.

  4. Bore and jack

    A cutting head on the first auger section turns inside the casing while the machine jacks the casing forward. The auger flights carry spoil back to the pit.

  5. Add sections

    The machine backs off, the next casing and auger sections are lowered in, joined and welded, and the cycle repeats.

  6. Finish

    At the receiving pit the cutting head is removed, the augers are withdrawn, and the carrier is installed on chocks.

SUDAS mentions a detail that affects friction: the first casing section may have a steel band welded around the top three-quarters of its circumference, which slightly over-excavates the hole so the following sections slide more easily. Because the augers rotate inside the casing, steel is the standard casing material; the carrier inside can be almost any pipe.

03 /What are auger boring's limits?

Auger boring working range (SUDAS Chapter 14)
FactorWhat SUDAS reports
Common sizes8 to 36 inches (about 203 to 914 mm); smaller jobs usually suit slurry or compaction methods, larger ones pipe jacking or tunnelling
Bore lengthOriginally 40 to 70 feet; typically 175 to 225 feet now; over 600 feet possible
AccuracyUsually ±1% of length; steerable equipment about ±0.1% vertically and ±1% horizontally
ObstaclesThe largest boulder that can pass the flights is about one third of the nominal casing diameter
Running sandLoose, sandy soils can flow into the casing ahead of the bore and cause settlement

Those limits explain where auger boring shines: medium casings under two-lane or four-lane roads in reasonably firm ground. They also explain its failure modes. A cobble bigger than the flights can take stops the bore; a sand lens below the water table can run into the casing and leave a void under the road.

04 /How does pipe ramming work?

Pipe ramming drives a steel pipe into the ground with a pneumatic hammer attached to its back end. SUDAS explains that the pipe can be rammed closed-ended in sizes up to about 8 inches, which displaces and compacts the soil like a mole but is harder and not normally recommended. More commonly, and always for larger sizes, the front is left open, so a cylinder of soil equal to the pipe's diameter enters the pipe as it advances.

  • Guide rails in the launch pit are set to the line and grade of the bore.
  • A steel band around the leading edge slightly over-excavates to reduce friction.
  • The hammer drives the pipe along the rails; further sections are welded on as it goes, or the whole length is welded up first when the site has room.
  • When the casing reaches the receiving pit, the soil core is removed by augering, compressed air or water jetting.

Steel is the only casing material strong enough to take the hammer's impact. SUDAS notes that ramming is often used under railway and road embankments for medium to large pipes, and that it can be quicker and cheaper than augering or drilling under the right conditions because its pits are smaller and installation is faster; for short bores of 60 feet or less it is generally less costly than directional boring, while drilling suits longer bores.

05 /What are pipe ramming's limits?

Pipe ramming working range (SUDAS Chapter 14)
FactorWhat SUDAS reports
Common sizes2 to 55 inches (about 51 to 1,397 mm); up to 147 inches has been done
Bore lengthUsually less than 150 feet (about 46 m); up to about 300 feet (91 m) successfully
AccuracyNon-steerable; usually better than ±1% of length
GroundAlmost all soils except solid rock; the leading edge tends to split cobbles, so it copes with rocky ground better than augering
Auger boring
Pipe ramming
Spoil
Removed during the bore
Removed afterwards
Steering
Limited; steered systems exist
None
Cobbles
Up to a third of the casing size
Better; the edge splits them
Pit
Long pit for track and machine
Smaller pit with guide rails
Length
Longer bores possible
Usually shorter

06 /Can auger boring or ramming install a gravity sewer?

Yes, through a casing, with care about tolerances. SUDAS works an example of a 12-inch sanitary sewer on a 1% grade bored 200 feet: with the ±0.2% tolerance common for gravity sewers, the job would likely need a significantly oversized casing with auger boring, or microtunnelling, to comply. Allowing ±12 inches instead would likely let a steered auger bore do the work without an oversized casing, at lower cost, while still meeting the sewer's minimum grade.

Line and grade accuracy of new-path methods over a 60 m boreA bar chart of the possible error in position over a 60 metre bore, using the tolerances in the Iowa SUDAS design manual. Impact moling cannot be steered and is not used for sewers. Pipe ramming, unsteered auger boring and directional drilling are typically within about one percent of the bore length, plus or minus 600 millimetres over 60 metres. Steered auger boring holds about a tenth of a percent vertically, 60 millimetres. Microtunnelling and pipe jacking can hold within about 25 millimetres. A reference line marks the 600 millimetres of total fall a 1 percent gravity sewer has over the same 60 metres. POSSIBLE ERROR AT THE FAR END OF A 60 m BORE (± mm) 0150300450600 IMPACT MOLINGnot steerable · not used for sewersNO LINE OR GRADE CONTROL ONCE STARTEDPIPE RAMMINGnon-steerable · ≈ ±1% of length±600AUGER BORINGunsteered · ≈ ±1% of length±600DIRECTIONAL DRILLING≈ ±1% of length±600STEERED AUGER (VERTICAL)≈ ±0.1% of length±60MICROTUNNEL / PIPE JACKINGwithin ≈ 25 mm (1 in)±25 TOTAL FALL OF A 1% SEWER OVER 60 m = 600 mm TOLERANCES: IOWA SUDAS DESIGN MANUAL CH. 14 · ARITHMETIC ONLY · REAL RESULTS DEPEND ON GROUND AND OPERATOR
Fig. 3Unsteered augering and ramming sit at about ±1% of length; steered augering improves to about ±0.1% vertically; laser-guided microtunnelling holds tens of millimetres.

The lesson for owners is to ask what tolerance is specified and why. Tight tolerances cost money; loose ones risk backfall. SUDAS also suggests building extra slope into gravity sewers through the length of a bore where possible, and placing manholes at both ends of long or difficult bores so small line and grade deviations can be corrected where the bore meets the open-cut sections. For tight gravity work, microtunnelling and pipe jacking is the step up.

07 /What about smaller bores: slurry and compaction methods?

Below the auger range, SUDAS describes slurry boring, which drills a pilot hole with fluid and reams it, most often for pipes of 2 to 12 inches over 40 to 75 feet, and compaction methods such as push rods and impact moles for pipes of about 6 inches or less. It notes that water jetting, which erodes a hole with a high-pressure jet, is rarely allowed by most jurisdictions because it over-excavates and causes settlement, and that some owners prohibit slurry boring because the hole is unsupported until the casing goes in. The small-service end is covered in moling and pipe pulling.

Casing crossings on private property are uncommon; they are mostly municipal, highway, rail and utility work, priced by tender. See municipal and commercial trenchless for how owners choose, and the Method Finder for how these methods rate against your crossing.

FAQQuestions people ask

What is an auger boring machine?

A track-mounted machine in a bore pit that jacks a steel casing forward while turning auger flights inside it to carry spoil back to the pit.

What is pipe ramming used for?

Mainly for driving steel casings under railway and road embankments over short distances, especially where cobbles would trouble an auger.

How accurate is auger boring?

SUDAS reports about ±1% of the bore length for standard equipment and about ±0.1% vertically for steerable auger equipment.

Can a casing be installed through rock?

Not by standard auger boring or ramming. Rock needs rock-capable drilling, microtunnelling with suitable cutters, or blasting and open excavation.

What goes inside the casing?

The carrier pipe, which can be almost any pipe material. It rests on chocks that centre it and allow its grade to be adjusted.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.