HAUSE SEWER NETWORKsewers@hause.ca403-679-3100
TrenchlessSewer.ca
New-path methods

Microtunnelling and pipe jacking: building gravity sewers on tight grade

How microtunnelling and pipe jacking work: jacking shafts, laser-guided boring machines, slurry spoil removal, sizes, accuracy, and Canadian sewer projects.

Short answer

Pipe jacking pushes a string of strong pipes through the ground from a jacking shaft while the face is excavated inside a shield at the front. Microtunnelling is remote-controlled pipe jacking: a laser-guided boring machine cuts the face, spoil is pumped out as slurry or augered back, and no one enters the bore. Both hold line and grade to within about 25 mm, which is why cities use them for gravity sewers.

Key takeaways
  • Microtunnelling is steerable, laser-guided and continuously supported at the face; SUDAS says installations within about one inch of line and grade are possible.
  • SUDAS gives microtunnelling pipe sizes of roughly 10 to 120 inches; man-entry pipe jacking typically starts at about 42 inches.
  • Both need a jacking shaft with a thrust wall and a reception shaft; short drives are expensive relative to their length.
  • Jacking pipe must take large compressive forces: steel, reinforced concrete, glass-fibre reinforced polymer mortar or vitrified clay.
  • Calgary is building most of its new 8.5 km TransCanada Sanitary Trunk by microtunnelling (as checked September 2026).
Microtunnelling between a jacking shaft and a reception shaftA deep jacking shaft on the left holds a jacking frame braced against a thrust wall. It pushes a string of concrete jacking pipes, and at the front a remote-controlled microtunnel boring machine cuts the face. A laser in the shaft projects onto a target in the machine for steering. Slurry lines carry spoil back to a separation plant on the surface, and the operator works from a control container. A reception shaft on the right receives the machine. No one works in the bore during routine operation. TRAFFIC, TREES AND SERVICES ABOVE STAY IN PLACE CONTROL SLURRY THRUST WALL JACKING FRAME MTBM LASER → TARGET IN THE MACHINE SLURRY FEED + RETURN RECEPTIONSHAFT REMOTE CONTROLLED · LASER GUIDED · CAN HOLD LINE AND GRADE WITHIN ~25 mm (SUDAS) SECTION · NOT TO SCALE
Fig. 1Microtunnelling: a remote-controlled, laser-guided boring machine is pushed from a jacking shaft by the pipe string behind it, with slurry carrying the spoil to the surface.

01 /What is pipe jacking?

Pipe jacking installs a pipeline by pushing it. The Iowa SUDAS design manual describes the set-up: pits at both ends, a guide rail or jacking frame to hold the pipe and jacks, and a thrust block, normally concrete, for the jacks to push against. A steel jacking shield leads the pipe string and gives workers a protected space to excavate the face, by hand or with machinery. Spoil goes back to the pit in small carts, augers or a conveyor. As each length of pipe is pushed in, the jacks retract, the next pipe is set in the pit, and the cycle repeats.

Steering is precise. A laser set to line and grade in the pit shines through the pipe onto a target at the face, and modern equipment adjusts automatically. Because people work at the face, SUDAS says man-entry pipe jacking and utility tunnelling are typically limited to pipes of 42 inches (about 1,067 mm) and larger, and 48 inches for extremely long drives. Length is theoretically unlimited: intermediate jacking stations spaced along the pipe let it be pushed in sections rather than all at once.

02 /How does microtunnelling work?

Microtunnelling takes the people out of the pipe. SUDAS defines it by four features: it is remote controlled from a panel usually on the surface; it is guided, normally by a laser projected onto a target in the machine; it is pipe jacked, with the machine and pipes pushed forward by a jacking system; and it is continuously supported, with pressure applied at the face to balance groundwater and earth pressure.

Microtunnelling between a jacking shaft and a reception shaftA deep jacking shaft on the left holds a jacking frame braced against a thrust wall. It pushes a string of concrete jacking pipes, and at the front a remote-controlled microtunnel boring machine cuts the face. A laser in the shaft projects onto a target in the machine for steering. Slurry lines carry spoil back to a separation plant on the surface, and the operator works from a control container. A reception shaft on the right receives the machine. No one works in the bore during routine operation. TRAFFIC, TREES AND SERVICES ABOVE STAY IN PLACE CONTROL SLURRY THRUST WALL JACKING FRAME MTBM LASER → TARGET IN THE MACHINE SLURRY FEED + RETURN RECEPTIONSHAFT REMOTE CONTROLLED · LASER GUIDED · CAN HOLD LINE AND GRADE WITHIN ~25 mm (SUDAS) SECTION · NOT TO SCALE
Fig. 2A microtunnel drive: jacking frame and thrust wall in the launch shaft, a string of jacking pipes, the boring machine at the face, laser guidance, slurry lines to a separation plant, and a reception shaft.
  1. Build the shafts

    A jacking shaft is sunk at one end with a thrust wall, and a reception shaft at the other. Shaft size depends on the machine and pipe length.

  2. Launch the machine

    The microtunnel boring machine is set on the jacking frame, aimed with the laser, and pushed through a seal in the shaft wall.

  3. Cut and jack

    The cutting head excavates the face while the jacks push the machine and the pipes behind it forward one length at a time.

  4. Remove spoil

    Soil is mixed with water into slurry and pumped to a separation plant on the surface, or removed by an auger inside a separate casing in the jacking pipe.

  5. Steer

    The operator reads the laser target and adjusts the machine's steering to hold line and grade.

  6. Receive

    The machine breaks into the reception shaft and is lifted out; the jacked pipe is the finished sewer or a casing for it.

03 /Why do cities choose microtunnelling for gravity sewers?

Because grade is everything in a gravity sewer and microtunnelling holds it. SUDAS describes microtunnelling, like pipe jacking, as laser-guided, steerable and highly accurate, with installations within about one inch of the proposed line and grade possible, and says it is normally used for pipelines that need high accuracy such as gravity storm and sanitary sewers. The other new-path methods are typically closer to ±1% of the bore length.

Line and grade accuracy of new-path methods over a 60 m boreA bar chart of the possible error in position over a 60 metre bore, using the tolerances in the Iowa SUDAS design manual. Impact moling cannot be steered and is not used for sewers. Pipe ramming, unsteered auger boring and directional drilling are typically within about one percent of the bore length, plus or minus 600 millimetres over 60 metres. Steered auger boring holds about a tenth of a percent vertically, 60 millimetres. Microtunnelling and pipe jacking can hold within about 25 millimetres. A reference line marks the 600 millimetres of total fall a 1 percent gravity sewer has over the same 60 metres. POSSIBLE ERROR AT THE FAR END OF A 60 m BORE (± mm) 0150300450600 IMPACT MOLINGnot steerable · not used for sewersNO LINE OR GRADE CONTROL ONCE STARTEDPIPE RAMMINGnon-steerable · ≈ ±1% of length±600AUGER BORINGunsteered · ≈ ±1% of length±600DIRECTIONAL DRILLING≈ ±1% of length±600STEERED AUGER (VERTICAL)≈ ±0.1% of length±60MICROTUNNEL / PIPE JACKINGwithin ≈ 25 mm (1 in)±25 TOTAL FALL OF A 1% SEWER OVER 60 m = 600 mm TOLERANCES: IOWA SUDAS DESIGN MANUAL CH. 14 · ARITHMETIC ONLY · REAL RESULTS DEPEND ON GROUND AND OPERATOR
Fig. 3The accuracy gap: about 25 mm for microtunnelling and pipe jacking, against up to ±600 mm over 60 m for methods held to about one percent of length.

It also copes with difficult ground. SUDAS says microtunnelling can handle a wide variety of soil conditions and that boulders or rocks up to 20 to 30 percent of the pipe diameter can normally be removed by the machine. The pressurised face limits ground loss below the water table, which is where open trenches and simpler bores run into trouble.

04 /What sizes and pipes does microtunnelling use?

Microtunnelling and pipe jacking at a glance (SUDAS Chapter 14)
FactorMicrotunnellingMan-entry pipe jacking
Pipe sizeAbout 10 to 120 inches (254 to 3,048 mm)Typically 42 inches (1,067 mm) and up
People in the boreNot for routine operationYes, at the face
AccuracyWithin about 1 inch of line and gradeWithin about 1 inch of line and grade
Pipe materialsSteel, ductile iron, reinforced concrete, glass-fibre reinforced polymer mortar, vitrified claySteel, reinforced concrete, glass-fibre reinforced polymer mortar, vitrified clay
ShapeCircular only (a boring machine cuts it)Circular with a boring machine; other shapes with other excavation methods
CostSpecialised; competitive on large projects, costly on short boresSignificant equipment investment

The name misleads: SUDAS notes that "micro" refers to the method's origin as pipe jacking for pipes too small for a person, and that the technique has since been used at very large diameters because removing people from the bore adds safety. The jacking pipe must survive the thrust, so it is a rigid pipe with a strong joint; often it is also the finished sewer.

05 /Where is microtunnelling used in Canada?

Large Canadian cities use it for trunk sewers and local sewers under built-up streets. Two examples we verified on municipal sites in September 2026:

  • Calgary, TransCanada Sanitary Trunk. The City describes a new 8.5 km underground wastewater pipe for Calgary, Cochrane and nearby communities, using pipes of 1.35 m and 1.5 m diameter, with more than 85 percent built by microtunnelling to limit surface disruption, preserve the sound barrier along 16 Avenue N.W. and protect existing trees. Construction began in spring 2025 with completion expected in early 2027.
  • Toronto, Fairbank-Silverthorn storm system. Toronto's basement-flooding project pairs a 4.5 m diameter, 2.4 km storm trunk tunnel built with a tunnel boring machine at depths of 15 to 40 m with new local storm sewers constructed by microtunnelling along several residential streets, supported by twenty shafts.

Both show the pattern: microtunnelling is chosen where the sewer must hold grade, the surface is valuable, and the drive is long enough to justify shafts. For how owners weigh those factors, see municipal and commercial trenchless, and for city-by-city notes, the across Canada page.

06 /What are the limits and risks?

  • Short drives. SUDAS says microtunnelling tends to be costly for relatively short bores, because the shafts, machine and separation plant cost much the same whatever the length.
  • Shaft space. Launch and reception shafts, a crane, a control unit and slurry separation need a work site, often a lane closure or a park corner for months.
  • Obstructions. Buried timber, steel or large boulders beyond the machine's capacity can stop a drive; recovery may need a rescue shaft.
  • Ground loss. Poor face-pressure control in wet ground can cause settlement above the tunnel.
  • Pipe damage. Jacking forces rise with length and friction; pipe joints must be designed for them, and lubrication is used on long drives.

Microtunnelling is a municipal and major-project method, priced by tender, so this site publishes no planning range for it. For smaller crossings, compare auger boring and pipe ramming and directional drilling; for the related pipe-eating technique that replaces an old sewer with microtunnelling equipment, see bursting, splitting and reaming.

07 /How does microtunnelling compare with other crossing methods?

Choosing a method for a new gravity sewer crossing (SUDAS figures)
FactorMicrotunnellingAuger boringDirectional drilling
Line and gradeWithin about 25 mmAbout ±1%; steered about ±0.1% verticallyAbout ±1% of length
Typical sizes254–3,048 mm203–914 mmUp to 1,524 mm
GroundwaterPressurised face copesRunning sand can cause settlementDrilling fluid supports the hole
Set-upTwo shafts, slurry plantLong bore pit, receiving pitRig and pipe string lay-down
Short drivesCostlyEconomicalEconomical for small pipes

The choice is usually made by grade first and cost second: if the sewer's slope leaves little room for error, the laser-guided methods win, and the question becomes whether the drive is long enough to carry the cost of the shafts.

FAQQuestions people ask

What is the difference between microtunnelling and pipe jacking?

Both push pipe from a jacking shaft. In pipe jacking, people excavate at the face inside a shield; in microtunnelling, a remote-controlled machine does it and no one enters the bore.

How accurate is microtunnelling?

SUDAS says installations within about one inch (25 mm) of the proposed line and grade are possible, which is why it suits gravity sewers.

What is the smallest pipe that can be microtunnelled?

SUDAS gives a range starting at about 10 inches (254 mm). Smaller gravity lines are usually done by guided boring, steered auger boring or open cut.

Is microtunnelling used for house connections?

Not usually. It is a method for sewers and trunks under streets, parks and highways. House laterals use lining, bursting or open cut.

Why does microtunnelling need a slurry plant?

In slurry systems, the cut soil is mixed with water and pumped to the surface, where a separation plant removes the solids so the water can be reused.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.